STS TRANSFER OPERATIONS
The STS transfer of chemical cargoes is
a common practice. Experience gained
from these regular operations has proven that STS transfers are safe, if proper procedures are
observed, in suitable weather and sea conditions.
In certain port areas it will be found that local regulations apply. These
local regulations should be followed and
where appropriate the recommendations made in this procedure can be used as additional advice.
ESTABLISH PERSON IN OVERALL CHARGE OF
THE STS OPERATION
The overall control of an STS operation
should be vested in the hands of one
individual and will be either one of the Masters concerned, or an
STS superintendent.
If both Masters are unfamiliar with, or
inexperienced in STS transfer operations then an STS superintendent must be
employed to assist ship’s masters in
mooring and unmooring of the ships, and to co-ordinate and supervise the entire ship-to-ship operation.
There are specialised STS agencies providing such services on an
international basis.
Master of the ship supposed to be
involved in STS transfer operation has to inform the chemical operator in order
to arrange necessary assistance. Master must satisfy himself that acceptable conditions for Ship to Ship (STS)
transfer exist.
There must be sufficient resilience in the moorings to absorb the movement between vessels
For all STS transfer operation Master remain responsible for
the safety of his own ship, its crew,
cargo and equipment and should not permit safety to be prejudiced by the actions of others. If
another ship fails to observe any of the
safety requirements during the STS transfer operation, this should be
brought to the attention of the Master
of the another ship and operation should be
suspended until the situation is rectified. To protect both vessels from damage, fenders must be of sufficient size and
strength, and be strategically placed, so as to:
1.absorb the impact energy during berthing/unberthing
2.maintain adequate separation between ships allowing for normal movement
and
listing.
Master of the ship involved in STS
transfer operation should ensure that the
ships to be used are compatible in design and equipment and that
mooring operations, hose handling and
communications can be conducted safely and
efficiently. The initial information will be supplied to the
organisers by the Master as per Check List 1 ( ICS / OCIMF
SHIP TO SHIP TRANSFER GUIDE
).
Additionally to Check List 1, the following should be determined prior to mooring:
whether approval from local authorities
have been received
the size and number of manifolds to be
used
whether the cargo cranes or derricks
are in satisfactory condition
whose hoses will be in use and last
pressure test of the hoses
which ship ( mother-ship or
daughter-ship ) has Yokohama fenders
STS On arrival at the terminal,
ships must confirm
with the terminal, the
wind speed restrictions applicable to the terminal
or berth i.e.:
--The maximum wind speed at
which the cargo is to be
stopped.
--The maximum
wind speed at which the cargo hoses are
to be disconnected.
--The maximum
wind speed at which the own ship is to cast off.
The above wind speed restrictions are to be notated in the ISGOTT Ship / Shore Checklist.
Good communication between the ships is
an essential requirement for successful
transfer operations. A common language for communication should be agreed before operations commence. If a
serious language problem be detected,
then action should be taken to resolve
this by transferring an experienced person from one ship to the other
before operations begin.
The ships should establish initial
communication as early as practicable to
plan operations and to confirm the transfer area.
As the ships come into the transfer area,
contact should be established on the
appropriate VHF channel at the earliest opportunity, thereafter
switching to a mutually agreed working
channel. Approach, mooring and unmooring should
not be attempted until proper effective communication has been
confirmed between two ships. At this
time, in accordance with the information
exchanged, Check List 2 and 3
should be satisfactory completed.
If communication breakdown occurs
during an approach manoeuvre, if
appropriate and safe, the manoeuvre should be aborted and the
subsequent actions taken by each ship
should be indicated by the appropriate sound
signals as prescribed in the IRPCS
(colreg).
During cargo transfer operation,
essential personnel on both ships should
have a reliable, common means of communication at all times, including a
backup system. Spare radios and batteries to be available on board.
The emergency signal should be agreed
between both ships and this should be a
series of short and rapid blasts on the ship whistle. It should be sounded by either ship in an emergency or in case of
communication breakdown during cargo
operations.
In general, operations should not be
resumed until satisfactory
communications have been re-established.
The lights and shapes to be shown, and
the sound signal made, during STS
transfer operations required by the
International Regulations for Preventing
Collisions at Sea.
MANOEUVERING
ALONGSIDE WITH TWO SHIPS UNDER POWER
One ship, normally the lager, maintain
steerage way at slow speed on a constant
heading. Normally the manoeuvre should be made with the wind and sea ahead, however local conditions and
knowledge may dictate an alternative
heading. It is recommended that the
manoeuvring ship approaches and berths
with her port side to the starboard side of the constant heading ship. The Master should always be
prepared to abort a berthing operations
if necessary. The decision should be taken in ample time while the situation is still under control.
A common method of berthing is for the
manoeuvring ship to approach the
constant heading ship from the quarter on the side of berthing. On
closer approach she should parallel the
course of the constant heading ship, about
50 to 100 meters off. The manoeuvring ship should then position itself
relative to the constant heading ship.
Contact is made by the manoeuvring ship
reducing the distance by appropriate rudder and engine movements until fenders touch.
The two ships should preferably make
parallel contact at the same speed with no
astern engine movements being necessary.
The effects of ship interaction should
be anticipated when manoeuvring at close
quarters.
On completion of mooring, the constant
heading ship will power all future
manoeuvres and, if a transfer at anchor is planned, will proceed to the
agreed anchoring position. During this
time the former manoeuvring ship will have its
engines stopped and rudder amidships. For this period the constant
heading ship should not use strong
astern engine movements.
Depends upon ships size and weather
condition it should be decided whether
only constant heading ship will anchor or both ship. The constant
heading ship should use the anchor on
the side opposite that on witch the other ship is moored.
Once at anchor, each ship is
responsible for keeping its own anchor watch.
MANOEUVRING
WITH ONE SHIP AT ANCHOR
This manoeuvre can be preferred for
more constrained transfer area,
especially when tug assistance is available.
A berthing operation should only be
carried out after the anchoring ship is
brought-up to her anchor and is lying on a steady heading with reference
to prevailing current and wind
conditions.
A careful watch should be kept on the
heading of the anchored ship and the
manoeuvring ship should be advised immediately by the anchored ship if
she has any tendency to yaw. Where there
is a tendency to yaw is excessively, a
tug should be employed to hold the anchored ship on a steady heading. If
no tug is available, postponement of the
operation should be considered.
The manoeuvring ship approach and berth
with her port side to the starboard side of the other ship. When approaching the
ship at anchor the wider angle of
approach than that adopted for manoeuvres underway is recommended. A wider angle of approach helps to avoid early
ship to ship contact in cases where the
anchored ship might yaw unexpectedly.
When mooring to an anchored vessel care
should be taken not to pull the anchored
vessel quickly towards the mooring vessel.
HOSE
HANDLING AND CARGO TRANSFER OPERATIONS
When two ships are securely moored the
pre-transfer Check List 4 should
be satisfactory completed. In addition, Ship/Shore Safety Check List to
be completed as well.
Cargo transfer operations should be
carried with the requirements of the
receiving ship.
The cargo transfer operation should be
planned and agreed in written between
the two vessels and should include information on the following where applicable:
quantity of each grade of cargo
sequence of grade
cargo density and temperature
number of pumps, maximum pressure
cargo heating requirements
initial, maximum and topping off rate
notice of rate change and transfer shut
down procedures
emergency and spill containment
procedures
watch or shift arrangements
critical stage of the operation
The agreed transfer rate should not
exceed the manufacturers recommended
flow rate for the cargo hoses.
Electrical bonding between the vessels’ hulls is not necessary.
Throughout cargo transfer operations,
the both ships should station a responsible person at the cargo manifold area
to observe the hoses and to check for
leaks. A responsible person equipped with portable radio should be stationed at or near the cargo pump controls
on the discharging ship to take action
as required.
Cargo transfer should begin at agreed
slow rate to enable the receiving ship
to check that the cargo pipelines system is correct set.
It should be noted that the incorrect
operations of pumps and valves can
produce pressure surges in a pipeline system. Consideration should be
given to the prevention of pressure
surges by careful planning and control of pump
speeds and the operation of valves.
During cargo transfer, appropriate
ballast operations should be performed in
order to minimise change in freeboard, and avoid excessive trim by the
stern.
Throughout the transfer, regular hourly
transfer rate checks and comparisons
should be made between the two vessels, and the results logged.
The transfer rate should be reduced to
an agreed topping off rate when the
receiving ship’s tanks are
reaching their feeling limit.
After completion of cargo transfer the
following operations should be carried
out:
All hoses drained into one ship prior
to disconnecting
Hoses disconnected, taking precautions
to ensure that no liquid is left in the
cargo transfer system
Cargo manifolds and cargo hoses
securely blanked
Authorities informed of completion of
cargo transfer and anticipated time of
unmooring
UNMOORING
Check
list 5 to be completed before unmooring.
Unmooring can be achieved by singling up fore and aft, then letting go
the remaining forward mooring and
allowing the bow to swing away from the constant heading ship to the suitable angle, at which time the remaining stern
mooring line is let to go and the
manoeuvring ship moves clear. After disengaging, neither ship should
attempt to steam ahead or fall astern of the
other until both ships are well separated.
It should be noted that local
conditions or vessel configuration may cause
difficulties in separating the two ships and other alternative plans
should be considered.
BEFORE
FILLING UP THE STS CHECK LIST IT IS IMPORTANT FOR MASTER TO VERIFY IF THE
CHARTERERS OF SHIPPER HAS GIVEN THE STS COORINATES IN WRITING TO ENSURE “
TERRITORIAL SEA AND EEZ “ RIGHTS OF NEIGHBOURING COUNTRIES ARE NOT INFRINGED.
SHIP TO SHIP TRANSFER MOORING
CHECKLISTS
|
||
PRE
STS TRANSFER CHECKLIST
|
Y/N/NA
|
|
Is the
parallel body length suitable for loaded/ ballast drafts?
|
||
Is the
freeboard suitable while coming alongside?
|
||
Considering
chemical tankers freeboards are low are height of fixed fenders suitable?
|
||
If
fixed fenders will crush railings are Yokohama fenders available?
|
||
If the
STS is planned underway can the ship maintain 5 knots for 2 hours minimum?
|
||
Are the ships lifting gear suitable for the
operation?
|
||
Do
both vessels have sufficient enclosed fairleads to prevent damage to
railings?
|
||
Are
the fairleads suitable for providing spring ropes?
|
||
If the
mooring ropes are wires are there proper synthetic tails?
|
||
Is the
vessel clear of any overhanging projections?
|
||
Is the
weather suitable?
|
||
Do you
have sufficient weighted heaving lines ?
|
||
Are
the mooring ropes being used floating on water?
|
||
Has
the transfer area and rendezvous area been agreed upon?
|
||
Is
there a basket for transporting personnel?
|
||
Have
methods of communication been agreed upon?
|
||
Is
sufficient crew available to handle mooring lines?
|
||
Has
the language of communications been agreed upon?
|
||
Has it
been agreed which ship will send which lines and in what sequence?
|
||
Will
both the ships be upright?
|
||
Will
the ships have suitable trim?
|
||
Has
the weather forecast been obtained?
|
||
Are
the STS transfer hoses in good condition?
|
||
Do the
fender ropes appear to be in good condition?
|
||
Has a
crew meeting been held?
|
||
Is
there a contingency plan and has it been agreed ?
|
||
Are
appropriate local authorities briefed of the operation?
|
||
Has a
navigation warning been issued?
|
||
Are
proper signals displayed?
|
||
Are
portable fenders available on the agreed side alongside?
|
||
PRE
MOORING CHECKLIST
|
||
Have
flags been put at the manifold?
|
||
Is
there somebody at the manifold to position the vessel ahead / astern ?
|
||
Are
secondary emergency prtable light fenders available?
|
||
Are the
cargo manifold connections ready and marked?
|
||
For
underway operations has the course and speed info been exchanged and
understood?
|
||
Is
lighting adequate at night?
|
||
Have
the mooring winches been tried out in advance?
|
||
Are
proper rope stoppers in place?
|
||
Are
anchors ready for immediate use?
|
||
Is the
course recorder on?
|
||
If the
mother ships is at anchor is her yaw being monitored and reported ?
|
||
Is
there a qualified and proficient helmsman available?
|
||
Is the
wind and tide direction/ strength being monitored?
|
||
PRE
UNMOORING CHECKLIST
|
||
Have
the cargo hoses been drained prior disconnection?
|
||
Are
all the hoses and manifolds blanked?
|
||
Is the
space between the ships clear of obstruction?
|
||
Has
the sequence of unmooring been agreed upon?
|
||
Is the
position of fenders suitable for the unmooring method?
|
||
Have
the mooring winches been tried out?
|
||
Is
crew standby at mooring stations?
|
||
Has
internal / external communications been tried out?
|
||
Has
local shipping movement been checked?
|
||
Have
the local authorities been notified?
|
Note: In case of negative answer pl
give brief reason if relevent
The lightering vessel, or support
tug shall make a navigational warning
prior to the commencement of lightening operations via VHF. If the situation warrants (poor visibility,
high traffic density, vessels drifting or slow steaming, etc.), voice warning
must be made at frequent intervals.
Operations must
be carried out in a safe manner and oil pollution must be avoided. these items
have first consideration over all other factors, and all the personnel onboard
shall be made aware of this.
The
vessel will, at all times, be capable of immediate manoeuvres while engaged in
the lightering operations. The main plant must not be immobilized at any time.
The vessel should conduct “break away
drills” prior to arrival to ensure that
officers and crew are fully aware of their stations and duties in a lightering
operation emergency.
If
the operation is carried out underway, full bridge and engine room watches are
to be maintained on throughout the operation. During still air conditions, a watch must be kept for lightning and thunder. STS loading/ unloading operations must stop immediately in such a scenario. Do NOT under estimate the danger posed by lightning.
IN THE EVENT OF A COMMUNICATIONS FAILURE OR THE
DEVELOPMENT OF AN EQUIPMENT FAILURE AFFECTING THE VESSEL, THE OPERATION SHALL
BE SUSPENDED UNTIL CORRECTIVE ACTION HAS BEEN COMPLETED.
Individual vessels may have lower
loading rate capability than the hoses, and the cargo transfer rate should be
set accordingly. Loading/discharge rates and manifold pressures are to be
monitored to ensure that the permitted rates are never exceeded.
In case oil escapes into the water, all cargo operations
shall be stopped immediately, the local authorities and the agent shall be
notified and the Vessel Response Plan or SOPEP activated as applicable.
Prior
to mooring, vessel should blow soot from boilers. During operations when ships
are moored together, tubes should not be blown.
Transfer of personnel between ships should be conducted with
the approval of the Masters and Lightering Master. Those personnel engaging in
transfer between the vessels (this includes the lightering support craft in
attendance) shall wear appropriate PPE and use an approved transfer basket
(e.g.: Billy Pugh type). Steadying lines shall be used to prevent the basket
swinging.
STS During ship-to-ship operations,
consideration must
be given to restricting the
use of
radars if
the relative freeboards
between the two ships might
expose the personnel working on deck
to electro-magnetic radiation from the radar scanners.
When transferring cargo to or
from barges it
is
essential
that
there
is no relaxation of
normal safety precautions and procedures. When conducting operations with barges due consideration should be given to the possibility
that
the
barge procedures may be
significantly
different to those used onboard the ship.
It may also be the case that the barge personnel are not
experienced seafarers or
tankermen. Extra
vigilance by the ship's staff may therefore be necessary to prevent an incident. If communication between ship and barge is lost for
any reason, the transfer operation must be stopped immediately.
Operations must not be resumed until
communications have
been re-established.
-------CAPT
AJIT VADAKAYIL ( 29 YEARS IN COMMAND )



looks like i got hacked again sir, this time they hacked my e-mail too.
ReplyDeletehi dhruv,
ReplyDeleteTurn off your computer when you are NOT using it.
Use a firewall.
If your computer has been hacked, alert your ISP and make them find out who did it.
capt ajit vadakayil
..